newsupdate

Approved road construction incomplete even after three years

The road construction work from Gendoli to Kapren has been pending for three years, causing great inconvenience to travelers. The road, which was supposed to be completed at a cost of 32 crore rupees, was supposed to be completed one and a half years ago, but due to the contractor’s negligence, it is still incomplete.

BundiOct 28, 2024 / 04:11 pm

Patrika Desk

The road construction work from Gendoli to Kapren has been pending for three years, causing great inconvenience to people traveling on this route.
The central road fund project, approved in 2021, sanctioned 32 crore rupees for the widening and strengthening of the 16.5 km road from Gendoli to Kapren. The work was supposed to start in January 2022, but after the CC road was built from Kapren to Jhali Ji Ka Barana, the construction work on the road from Gendoli to Jhali Ji Ka Barana has not even started yet.

Three years of dug-up road

The five-kilometer-long paved road from Gendoli to Jhali Ji Ka Barana has been dug up for two and a half years. The condition of the road has become worse than a dirt track. Vehicle drivers are getting injured by falling into potholes, and the situation becomes even more critical during the rainy season.

Work completion deadline passed one and a half years ago

The work on this road was supposed to be completed by April 2023, but due to the contractor’s negligence, the road construction has not been completed even after one and a half years of the deadline.
Local leaders and public works department officials remain silent when asked about the matter.

News / newsupdate / Approved road construction incomplete even after three years

Copyright © 2024 Patrika Group. All Rights Reserved.